View:2 Date:2020-09-08
Name of Project: 1.76 MTPA Full Energy Recovery Clean Stamp-Charging Intelligent Heat Recovery Coke Oven and CDQ Project of Tangshan Guotang Steel Co., Ltd.
Service: EPC
Capacity: 2×130t/h
Type of Coke Oven: CHS-2019 Full Energy Recovery Clean Stamp-Charging coke oven
Start of Construction: September 2020
Planned Restart Month: 1# October 2026; 2# January 2027